P and Q can do a work in 12 days. Q and R can do the same work in 16 days, and R and P can do it in 24 days. Find the time in which P, Q and R can finish the work together.

A. 9(3/4) days

B. 10 days

C. 11(1/4) days

D. 10(2/3) days